Project:
6721 Ryesonggang Hydropower Plant No.4, DPR Korea
- Issuance Request
Project | 6721: Ryesonggang Hydropower Plant No.4, DPR Korea |
---|---|
ISSUANCE STATUS | Issued (on 14 Oct 16) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Dec 12 - 31 Mar 16 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
0
CERs issued from 01 Jan 2013 until 31 December 2020: 27,807 Total amount of CERs: 27,807
Serial Range:
Block start: KP-5-15801-2-2-0-6721
Block end: KP-5-43607-2-2-0-6721
|
Verification and certification reports |
VVS/VVM version:
VVS 9.0
![]() ![]() |