Project: 5831 Providencia Hydroelectric Plant - Issuance Request
Project 5831: Providencia Hydroelectric Plant
 
ISSUANCE STATUS Issued (on 29 Jun 23)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Oct 12 - 30 Sep 19
Monitoring report Monitoring report (1064 KB)
 
Request for issuance Signed form (133 KB)
Amount of CERs CERs issued up to 31 December 2012: 1,583
CERs issued from 01 Jan 2013 until 31 December 2020: 148,204
Total amount of CERs: 149,787
Serial Range: Block start: CL-5-43304011-2-2-0-5831     Block end: CL-5-43452214-2-2-0-5831
Serial Range: Block start: CL-5-43452215-1-1-0-5831     Block end: CL-5-43453797-1-1-0-5831
Verification and certification reports VVS/VVM version: VVS-PA 3.0
Certification report (398 KB)
Verification report (398 KB)
Additional documents ER spreadsheet (19 KB)
5831_ER sheet_final for submission (267 KB)
Monitoring report (1318 KB)