07:27 09 Jan 25
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | BRASCARBON Methane Recovery Project BCA-BRA-04A. (5484) |
---|---|
DOE that requested for issuance and date of request | ICONTEC (30 Jun 21) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
1) The monitoring report and the verification report describe that parameter “flame detection on the flare in a minute (Flamem)” was measured using minute-by-minute thermocouples, whereas the applied methodological tool “Project emissions from flaring”, version 03.0 (Data / Parameter table 10) requires that the parameter be determined using a flame detector (Ultra Violet detector or Infra-Red or both) and the approved monitoring plan requires that the measurement be made using a fixed installation optical flame detector. The DOE is requested to substantiate (i) how it verified the monitoring of Flamem in compliance with the approved monitoring plan and the applied Tool for this monitoring period and (ii) why it did not consider a permanent change to the monitoring plan or a temporary deviation from the Tool and the monitoring plan, prior to submitting the request for issuance. Please refer to Please refer to Paragraph 360 of the VVS-PA ver. 02. | |
Date | 11 Oct 21 |