08:26 05 Jul 25
Project:
5275 Dehe Zhangbei Phase II Wind Farm Project
- Issuance Request
Project | 5275: Dehe Zhangbei Phase II Wind Farm Project |
---|---|
ISSUANCE STATUS | Issued (on 04 May 22) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jul 15 - 13 Nov 18 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
315,618
Serial Range:
Block start: CN-5-1133816111-2-2-0-5275
Block end: CN-5-1134131728-2-2-0-5275
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 3.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: