07:04 09 Oct 24
Project:
5023 Redevelopment of Tana Hydro Power Station Project
- Issuance Request
Project | 5023: Redevelopment of Tana Hydro Power Station Project |
---|---|
ISSUANCE STATUS | Issued (on 06 Feb 15) completeness check: complete | info & rep check: concluded |
Monitoring period | 11 Oct 11 - 31 Dec 12 |
Monitoring report | Monitoring report (759 KB) |
Status of a monitoring report | The DOE has raised one or more corrective action requests or clarification requests, for which no response has been received from the project participant or the coordinating/managing entity |
Request for issuance | Signed form (128 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
18,677
Serial Range:
Block start: KE-5-217845-1-1-0-5023
Block end: KE-5-236521-1-1-0-5023
|
Verification and certification reports |
VVS/VVM version:
VVS 6.0
Certification report (904 KB) Verification report (904 KB) |
Additional documents |
5023 1 Monitoring Report (320 KB)
5023 1 CER Calculation (26 KB) 5023 1 GEF Calculation 2011 (3107 KB) 5023 1 GEF Calculation 2012 (13 MB) |
Offset now: visit the United Nations Carbon Offset Platform