18:16 01 Aug 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 4955 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Dak Me 1 Hydropower Project in Vietnam |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1) The input values for the investment analysis have been based on a FSR for a 4MW project activity. As the installed capacity has been revised to 5MW (after information and reporting check), power density and plant load factor (PLF) have been updated. However as the original input values have been based on the FSR for a 4 MW project, the DOE is requested to validate (a) the suitability of the input values for the 5 MW installed capacity and (b) the PLF and net electricity generation. In doing so, the DOE is requested to clarify the change in the PLF from 54.2% to 43.7% in the most recent submission. Please refer to VVM paragraph 114(a). | |
Date | 12 Oct 12 |