02:50 11 Feb 25
Project:
4687 Zafarana 85 MW Wind Power Plant Project
- Issuance Request
Project | 4687: Zafarana 85 MW Wind Power Plant Project |
---|---|
ISSUANCE STATUS | Issued (on 06 Aug 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 08 Aug 11 - 31 Dec 12 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
140,655
Serial Range:
Block start: EG-5-11050950-1-1-0-4687
Block end: EG-5-11191604-1-1-0-4687
|
Verification and certification reports |
VVS/VVM version:
VVS 3.0
![]() ![]() |