Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 4274 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | SF6 recovery and reclamation project, South Korea |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. Why is only SFK mentioned in the PDD as the project participant, while in other part of the PDD it is clear that both SFK and KERI are involved and included in the project boundary? 2. The PDD indicates in chapter A.4.3.E that SF6 can also be disposed off and the graph of the project boundary in para B.3 also refers to incineration, which is however outside the project boundary. Please clarify whether all relevant flows of SF6 are properly included in the project boundary. 3. The requirements for the ex-ante baseline setting refer to a year’s data, while in this case only 8 months are available. How did the DOE properly validate that the requirement has been met? |
|
Date | 08 Mar 11 |