19:02 09 Jan 25
Project:
4052 Horcones biomass power plant expansion project
- Issuance Request
Project | 4052: Horcones biomass power plant expansion project |
---|---|
ISSUANCE STATUS | Issued (on 24 Jul 15) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 13 - 31 Dec 13 |
Monitoring report | Monitoring report (1183 KB) |
Status of a monitoring report | The DOE has raised one or more corrective action requests or clarification requests, for which no response has been received from the project participant or the coordinating/managing entity |
Requests for post-registration changes submitted with the issuance request | PRC-4052-002 |
Request for issuance | Signed form (1838 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
87,244
Serial Range:
Block start: CL-5-21594187-2-2-0-4052
Block end: CL-5-21681430-2-2-0-4052
|
Verification and certification reports |
VVS/VVM version:
VVS 7.0
Certification report (2866 KB) Verification report (2866 KB) |
Additional documents |
4052 1 Monitoring Report (1407 KB)
4052 1 CER Calculation (208 KB) |
Offset now: visit the United Nations Carbon Offset Platform