Project title of the project activity or programme of activities (PoA) for which issuance is requestedHuadian Guangzhou Higher Education Mega Center LNG-fired Power Generation Project in China (3786)
DOE that requested for issuance and date of requestERM CVS (10 Nov 11)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
1) The DOE is required to clarify the calculation of the EF Coal, Adv, CH4 in the MR and Excel spreadsheet which is based on an ex-ante value of  “Unit Standar Coal consumption (CC Coal, Adv)” that differs from the one indicated in the registered PDD. Please refer to Paragraphs 208 - VVM v. 1.2.
Date 03 Jan 12