08:22 10 Feb 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 3184 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Bio-mass (Rice Husk) based Cogeneration project at M/s Rayana Paper Board Industries Ltd. (RPBIL), Vill: Dhaurahra, Post: Digha, Distt: Sant Kabir Nagar- 272 175, Uttar Pradesh |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to confirm how it has validated that the project activity is not more attractive than the pre-project scenario. Further the unit cost comparison should be cost per kWh and not cost per kWhth. 2. The DOE should clarify how it has validated that the proposed baseline is credible and realistic and what steps have been taken to acquire a coal based boiler. 3. The DOE should confirm the remaining lifetime for the existing low pressure rice husk based boiler. 4. The DOE should clarify the inconsistency in the efficiency of the baseline unit (coal based cogeneration plant) as investment comparison analysis considers 80% efficiency, whereas baseline emission considers 60% efficiency. |
|