11:12 06 Jul 25
Project:
3122 Jilin Longyuan Changling Shuanglong Phase I Wind Power Project
- Issuance Request
Project | 3122: Jilin Longyuan Changling Shuanglong Phase I Wind Power Project |
---|---|
ISSUANCE STATUS | Issued (on 11 Sep 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 26 Nov 10 - 24 Jan 11 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
9,428
Serial Range:
Block start: CN-5-601676203-1-1-0-3122
Block end: CN-5-601685630-1-1-0-3122
|
Verification and certification reports |
VVS/VVM version:
VVM 1.2
![]() ![]() |