15:54 27 Dec 24
Project:
3088 Baiyun’ebo 45MW Wind farm Project
- Issuance Request
Project | 3088: Baiyun’ebo 45MW Wind farm Project |
---|---|
ISSUANCE STATUS | Issued (on 02 Aug 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 08 May 10 - 28 Feb 11 |
Monitoring report | Monitoring report (268 KB) |
Request for issuance | Signed form (491 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
71,011
Serial Range:
Block start: CN-5-585237982-1-1-0-3088
Block end: CN-5-585308992-1-1-0-3088
|
Verification and certification reports |
VVS/VVM version:
VVM 1.2
Certification report (54 KB) Verification report (2203 KB) |
Additional documents | Monitoring Report (256 KB) |
Offset now: visit the United Nations Carbon Offset Platform