04:05 13 May 25
Project:
2772 10 MW Biomass Power Generation Project - Tokyo Cement, Trincomalee
- Issuance Request
Project | 2772: 10 MW Biomass Power Generation Project - Tokyo Cement, Trincomalee |
---|---|
ISSUANCE STATUS | Issued (on 24 Aug 16) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 15 - 31 Dec 15 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
36,539
Serial Range:
Block start: LK-5-882537-2-2-0-2772
Block end: LK-5-919075-2-2-0-2772
|
Verification and certification reports |
VVS/VVM version:
VVS 9.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: