18:57 10 Jan 25
Project:
2772 10 MW Biomass Power Generation Project - Tokyo Cement, Trincomalee
- Issuance Request
Project | 2772: 10 MW Biomass Power Generation Project - Tokyo Cement, Trincomalee |
---|---|
ISSUANCE STATUS | Issued (on 24 Apr 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Nov 10 - 30 Apr 12 |
Monitoring report | Monitoring report (543 KB) |
Request for issuance | Signed form (80 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
50,788
Serial Range:
Block start: LK-5-298787-1-1-0-2772
Block end: LK-5-349574-1-1-0-2772
|
Verification and certification reports |
VVS/VVM version:
VVS 3.0
Certification report (812 KB) Verification report (812 KB) |
Additional documents |
2772-MR-2013 02 18 (991 KB)
2772-3_ER excel sheet_TCCL_Nov 2010 to April 2012- 2013 02 18 (91 KB) |
Offset now: visit the United Nations Carbon Offset Platform