21:33 19 Nov 25
Project:
2705 Hangzhou Huadian Banshan Power Generation Co., Ltd.’s Natural Gas Power Generation Project
- History
| Project | 2705: Hangzhou Huadian Banshan Power Generation Co., Ltd.’s Natural Gas Power Generation Project |
|---|---|
| Request for review |
Request 1
Request 2 Request 3 EB meeting: EB56 (at which the Board considers the request(s) for review, decides whether to undertake the review and, if so, determine its scope and selects a review team) Initial comments: 2705 RfR DNV response (80 KB)
2705 RfR PP response (47 KB)
2705 RfR levelised cost revised calc (141 KB)
|
| Review |
Scope (130 KB)
EB meeting: EB58 (at which the report of the review team was/will be considered) |
Data before corrections
| CDM-PDD |
project design document (862 KB)
PDD appendices Appendix 1 - ER Sheet 2705 (72 KB)
Appendix 2 - Electricity Sheet 2705 (141 KB)
Appendix 3 - IRR Sheet 2705 (171 KB)
|
|---|---|
| Validation Report |
Validation report (1492 KB)
|
Data before approval of the request for post-registration changes on 22 Nov 2012
| Link to PRC form | PRC |
|---|---|
| CDM-PDD |
project design document (1543 KB)
PDD appendices Appendix 1 - ER Sheet 2705 (72 KB)
Appendix 2 - Electricity Sheet 2705 (141 KB)
Appendix 3 - IRR Sheet 2705 (171 KB)
|

2705 RfR DNV response
2705 RfR levelised cost revised calc
Offset now: visit the United Nations Carbon Offset Platform