02:28 18 May 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2677 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Sichuan Furong Coal Mine Methane Utilization Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE is requested to justify the following input values: (a) the ratio of electricity that the project activity displaces, specifically the annual amount of electricity used by the coal mines, the amount produced by the waste coal plant, the amount imported from the grid and the basis for the 43.89 GWh/year; (b) the average tariff of 0.286 RMB/kWh, the costs of the waste coal captive plant at 0.229 RMB/kWh; (c) income due to selling/saving heating to households and mines; and (d) the cost details of the compared similar activities in the province. In doing so, refer to VVM, v1, paragraphs 111 and 112. 2. The DOE is requested to justify the changes made to the IRR input values of the PDD (v3, 1 May 2008) against the PDD (v6.2, 15 May 2009) submitted for registration. 3. The DOE is requested to further explain how it has validated: (a) the baseline conditions of the project activity; and (b) the elimination of the baseline alternatives. In doing so refer to VVM, v1, paragraphs 80, 81, 86 and 87. The calculation details of the investment comparison analysis should be provided. 4. The DOE is requested to validate the ex-ante parameters (VR, p20) used for the baseline estimation. 5. The DOE is requested to justify why the quantity of CMM use for heating (mine facility/households) is not included in the monitoring plan. |
|
Date | 30 Oct 09 |
Offset now: visit the United Nations Carbon Offset Platform