13:19 21 May 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2461 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | BFG-fired Power Generation Project in Baosteel Co Ltd., Shanghai, P. R. China. |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. The DOE shall substantiate: (i) how the assumed priced of natural gas represent the market values of natural gas at the time of the investment decision, (ii) why demand/capacity charge, if it has been paid in the pre-project scenario by the PP, has not been considered as revenue in the investment analysis. 2. The PP/DOE shall: (i) substantiate suitability of applied financial indicator, equity NPV, in the investment comparison analysis in accordance with sub-step 2b (Option II) and 2c of the Tool for the demonstration and assessment of additionality version 5.2, and (ii) verify the accuracy of equity NPV calculations carried out for investment comparison analysis in compliance with paragraphs 109 of VVM. 3. The PP/DOE shall substantiate on how the electricity generated in the affiliated top gas pressure recovery turbine (TRT) is taken into account in calculating the emission reduction in line with the methodology. The historical data of electricity generation from TRT should be provided. 4. The PP/DOE shall clarify how the additional BFG requirement to industrial facility due to installation of the 4#BF can be met by surplus waste BFG generated by other three blast furnaces (1#BF, 2#BF and 3#BF) as it appears that there is only 1% BFG available to be flared out of total waste BFG generated by other three blast furnaces in according to the BFG statistics in 2004 (VR pg 16). Further the PP/DOE should provide the detailed information of existing coal power plants such as installed capacity, historical coal and waste BFG consumption, etc. 5. The means of calculation of QBL,product is not in accordance with ACM0012 version 2. The DOE is requested to clarify why a Corrective Action Request was not raised during the validation. 6. The PP/DOE shall provide the revised monitoring plan including the monitoring of electricity imports from the grid to the project activity, the electricity generated by the TRT, and electricity imports from the TRT. 7. The last portion of Page 15 and top portion of Page 16 of the PDD submitted for request for registration have been deleted. The PP/DOE should submit the revised PDD correcting this corruption. |
|
Date | 27 Jul 09 |