16:58 07 Sep 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2441 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | Shanxi Wulushan 1st phase Wind Power Project |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. Further clarification is sought on how the DOE has validated that the investment analysis is in line with EB 38, para 54 (b) as using a tariff of 0.71 RMB/kWh produces an IRR of 7.76% and not 9.76%. 2. The DOE should confirm how the input values to the investment analysis have been validated based on EB 38, para 54(c). 3. Further clarification is sought what “other expenses” are in the investment analysis. 4. The DOE is requested to confirm the appropriateness of the electricity tariff assumed in the FSR/PDD, in comparison with previous tariff notifications since 2002 in the same region and whether such information was available at the time the FSR was prepared. 5. Further clarification is sought why only project activities built after 2005 have been considered in the common practice analysis. |
|
Date | 08 Jun 09 |