23:52 10 May 25
Registration Request for Review Form
CDM project activity/programme of activities registration request review form (CDM-REGR-FORM) (Version 03.0) |
---|
Reference number of the proposed CDM project activity/programme of activities (PoA) submitted for registration | 2199 |
---|---|
Title of the proposed CDM project activity/PoA submitted for registration | 48 MW Duduluo River Hydroelectric Power Plant |
Please indicate, in accordance with paragraphs 37 and 40 of the CDM modalities and procedures, which validation requirement(s) may require review. A list of requirements is provided below. Please provide reasons in support of the request for review. Including any supporting documentation. | |
The following are requirements derived from paragraph 37 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() ![]() |
|
The following are requirements derived from paragraph 40 of the CDM modalities and procedures: | |
![]() ![]() ![]() ![]() ![]() ![]() |
|
![]() |
|
Additional information | |
1. Further clarification is required on how the DOE has validated the suitability of the input values to the investment analysis, as per the guidance of EB 38 paragraph 54(c). 2. Further clarification is required how the DOE has validated the common practice analysis, in particular, the scale of similar project activities and the essential distinction between the project activity and similar projects considered based on higher unit cost. In addition, the DOE should clarify the inconsistency between the PDD and the Validation Report on the common practice analysis. |
|
Date | 22 Jan 09 |