Project:
2149 Diaobingshan New-built 49.5MW Wind Power Station Project
- Issuance Request
| Project | 2149: Diaobingshan New-built 49.5MW Wind Power Station Project |
|---|---|
| ISSUANCE STATUS | Issued (on 27 Jan 12) completeness check: complete | info & rep check: concluded |
| Monitoring period | 07 May 10 - 30 Jun 11 |
| Monitoring report |
Monitoring report (170 KB)
|
| Request for issuance |
Signed form (590 KB)
|
| Amount of CERs |
CERs issued up to 31 December 2012:
98,768
Serial Range:
Block start: CN-5-504044372-1-1-0-2149
Block end: CN-5-504143139-1-1-0-2149
|
| Verification and certification reports |
Certification report (100 KB)
Verification report (573 KB)
|
| Additional documents |
MR Diaobingshan 3rd VER (175 KB)
CER Diaobingshan 3rd VER (30 KB)
|