Project:
2033 Jiadu River Zhentong Power Plant Project
- Issuance Request
Project | 2033: Jiadu River Zhentong Power Plant Project |
---|---|
ISSUANCE STATUS | Issued (on 13 Jan 11) |
Monitoring period | 09 Mar 09 - 25 Jul 10 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
28,113
Serial Range:
Block start: CN-5-272432842-1-1-0-2033
Block end: CN-5-272460954-1-1-0-2033
|
Verification and certification reports |
![]() ![]() |
Additional documents |
![]() ![]() |