19:54 07 Jul 25
Project:
2027 Inner Mongolia Bayinhanggai 49.5MW Wind Farm Project
- Issuance Request
Project | 2027: Inner Mongolia Bayinhanggai 49.5MW Wind Farm Project |
---|---|
ISSUANCE STATUS | Issued (on 29 Apr 10) |
Monitoring period | 23 Nov 08 - 31 Aug 09 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
90,454
Serial Range:
Block start: CN-5-199225582-1-1-0-2027
Block end: CN-5-199316035-1-1-0-2027
|
Verification and certification reports |
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform