05:23 29 Dec 25
Project:
2012 Gansu Zhuoni Niuzi 30MW Hydropower Project
- Issuance Request
| Project | 2012: Gansu Zhuoni Niuzi 30MW Hydropower Project |
|---|---|
| ISSUANCE STATUS | Issued (on 11 Dec 15) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Jan 13 - 26 Feb 15 |
| Monitoring report |
Monitoring report (342 KB)
|
| Request for issuance |
Signed form (392 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
199,344
Serial Range:
Block start: CN-5-957602559-2-2-0-2012
Block end: CN-5-957801902-2-2-0-2012
|
| Verification and certification reports |
VVS/VVM version:
VVS 9.0