08:04 11 May 25
Project:
1949 29.7 MW Wind Power project in Karnataka, India
- Issuance Request
Project | 1949: 29.7 MW Wind Power project in Karnataka, India |
---|---|
ISSUANCE STATUS | Issued (on 29 Jun 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 11 - 31 Dec 11 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
97,126
Serial Range:
Block start: IN-5-142735202-1-1-0-1949
Block end: IN-5-142832327-1-1-0-1949
|
Verification and certification reports |
![]() ![]() |
Additional documents |
![]() ![]() |
Previous submissions
Submission date | Outcome |
---|---|
03 Apr 12 | CC incomplete |