05:35 16 Jul 25
Project:
1926 Fuxin CMM/CBM Utilization Project in Liaoning Province
- Issuance Request
Project | 1926: Fuxin CMM/CBM Utilization Project in Liaoning Province |
---|---|
ISSUANCE STATUS | Issued (on 15 Jan 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Dec 10 - 31 Jul 11 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
366,528
Serial Range:
Block start: CN-5-718680113-1-1-0-1926
Block end: CN-5-719046640-1-1-0-1926
|
Verification and certification reports |
VVS/VVM version:
VVM 1.2
![]() ![]() |
Additional documents |
![]() |
Previous submissions
Submission date | Outcome |
---|---|
02 Jul 12 | CC complete | I&R incomplete |