Project: 1535 Changwa 10 MW Small-scale Hydro Project - Issuance Request
Project 1535: Changwa 10 MW Small-scale Hydro Project
 
ISSUANCE STATUS Issued (on 24 May 13)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jan 12 - 31 Dec 12
Monitoring report Monitoring report (137 KB)
 
Request for issuance Signed form (94 KB)
Amount of CERs CERs issued up to 31 December 2012: 29,459
Serial Range: Block start: CN-5-820055142-1-1-0-1535     Block end: CN-5-820084600-1-1-0-1535
Verification and certification reports VVS/VVM version: VVS 3.0
Certification report (575 KB)
Verification report (575 KB)
Additional documents 2012_Changwa(Ref.1535)_4th_ERs_spreadsheet_Version_02.2 (77 KB)
20130314_Changwa_Ref.1535__4th_MR_Version_02.3_clean (154 KB)