| Project title of the project activity or programme of activities (PoA) for which issuance is requested | Ganluo Kaijianqiao Hydropower Project, P.R.China (1432) |
|---|---|
| DOE that requested for issuance and date of request | TÜV NORD (17 Aug 09) |
| Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
| Incompetence | |
| Please indicate reasons for the request for review | |
|
OTHER ISSUES:
1) The DOE verified the calibration certificates dates from Revenue Meter, Mose Meter and Backup Meter as 24/04/2009, which are beyond the end of the monitoring period, and stated in the verification report that the calibration records which covered this monitoring period were assessed to be credible and appropriate. Clarifications are required on whether previous calibrations were made in accordance with the frequency presented in the revised monitoring plan (i.e. yearly). 2) The PP/DOE are required to clarify why the readings of the Mose Meter were not reported neither on 25/12/2008 nor on 31/12/2008 and why the readings from the backup meters Meter M1 and Meter M2 were not used instead. |
|
| Date | 28 Oct 09 |