10:09 05 Feb 26
Project:
1424 Carhuaquero IV Hydroelectric Power Plant
- Issuance Request
| Project | 1424: Carhuaquero IV Hydroelectric Power Plant |
|---|---|
| ISSUANCE STATUS | Issued (on 08 Jul 11) |
| Monitoring period | 03 May 08 - 31 Dec 08 |
| Monitoring report |
Monitoring report (318 KB)
|
| Request for issuance |
Signed form (714 KB)
|
| Amount of CERs |
CERs issued up to 31 December 2012:
10,040
Serial Range:
Block start: PE-5-609612-1-1-0-1424
Block end: PE-5-619651-1-1-0-1424
|
| Verification and certification reports |
Certification report (44 KB)
Verification report (2200 KB)
|
| Additional documents |
Monitoring Report (1681 KB)
|

Monitoring report
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: