Issuance Request for Review Form


CDM project activity/programme of activities
issuance request review form (CDM-ISSR-FORM)
(Version 03.0)

Project title of the project activity or programme of activities (PoA) for which issuance is requestedJiangxi Fengcheng Mining Administration CMM Utilization Project (1135)
DOE that requested for issuance and date of requestTÜV SÜD (05 Nov 08)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
1. The monitoring report shows that 6,502,358.50 m3 of CH4 was consumed to produce 16,735.08 MWh of electricity during this monitoring period. However, the PDD indicates that in order to produce the same quantity of the electricity (16,735.08 MWh) the power plant requires less than the methane consumption reported in the monitoring report. Further clarification is required, since this discrepancy raises questions on either the efficiency of power production or on a possible venting or flaring of surplus methane.
2. Further clarification is required on how the DOE verified 0.98% and 0.985% of NMHC concentration conducted in August 2007 and April 2008.
3. Annex I of the verification report does not refer to this project activity but refer to the validation protocol of PA 1963. Further clarification is required.
Date 06 Jan 09