01:12 27 Apr 25
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Wuxi Taohuashan Landfill Gas to Electricity (0856) |
---|---|
DOE that requested for issuance and date of request | SGS (16 Aug 10) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
It was observed that the DOE performed a “Preliminary Verification” prior to the first periodic verification. However, the “Preliminary Verification” and the on-site visit of the first periodic verification (conducted on 28-29/07/2008 and 27-28/02/2009, respectively) were done prior to the publication of the monitoring report version 1 (27/04/2009). Paragraph 62 of the Modalities and Procedures of the CDM stipulates that a DOE may only conduct verification activities after it has made the monitoring report publicly available. The DOE shall clarify why it has not conducted the verification in accordance with the requirements of paragraph 62 of the Modalities and Procedures of the CDM. | |
Date | 18 Dec 10 |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: