01:21 01 Jun 26
Issuance Request for Review Form
|
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
|---|
| Project title of the project activity or programme of activities (PoA) for which issuance is requested | Passo do Meio, Salto Natal, Pedrinho I, Granada, Ponte and Salto Corgão Small Hydroelectric Power Plants - Brascan Energética S.A. Project Activity (0519) |
|---|---|
| DOE that requested for issuance and date of request | BVI (16 Mar 09) |
| Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
| Incompetence | |
| Please indicate reasons for the request for review | |
|
1.The Verification Report (VR, p.23, 28) states that the calibration for one of the meters, i.e. meter 00069901 was valid for 2 years and the recalibration was delayed from February 2007 to March 2008. Clarification is required on how the DOE has closed the issue concerning the impact of delayed calibration without making the most conservative assumption. 2. Clarification is required on whether the DOE has verified all of the data, as the VR (p.10) states that “there were verified 33% of the available data and all were in accordance with the monitoring plan.” |
|
| Date | 09 Apr 09 |