02:27 29 Apr 24
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | “Blended cement with increased blend” at Orient cement’s Devapur and Jalgaon plants in India (0456) |
---|---|
DOE that requested for issuance and date of request | SGS (24 Oct 08) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
1. The monitoring report stated that the cement grinding capacity is being upgraded to 3 million tonnes/year in Devapur Unit and to 2.22 million tonnes/year in Jalgaon Unit. However, the capacity stated in the registered PDD is 1.7 and 0.7 million tonnes/ year for the two Units respectively. Further clarification is required on how the DOE verified that the project was implemented in accordance with the PDD. 2. Other issue: The calibration dates for all measuring instruments are required to be provided. |
|
Date | 08 Nov 08 |