Issuance Request for Review Form


CDM project activity/programme of activities
issuance request review form (CDM-ISSR-FORM)
(Version 03.0)

Project title of the project activity or programme of activities (PoA) for which issuance is requestedPuente Gallego Landfill gas recovery project, Gallego, Rosario, Argentina. (0431)
DOE that requested for issuance and date of requestSGS (16 Jul 08)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
1. The monitoring reported stated that during the failure of the flow meter, the LFG flow was calculated as the average flow of the last 7 days:
1.1) Further information is required on the LFG flow meter outage time during this monitoring period;
1.2) Further clarification is required on how the DOE verified that this is in accordance with the revised monitoring plan and the methodology.
2. The spreadsheet shows that there are a number of days, (e.g. on 02/05/07 and 02/06/07etc.) when the LFG flared is more than the LFG collected. Further clarification is required.

Other Issues
3. Further clarification is required on the status of implementation of electricity generating equipment as no LFG was sent for electricity generation, whereas the verification report (p.9) mentions that project includes installation of both flare and electricity generating equipments.

Date 20 Aug 08