01:41 04 Jan 26
Issuance Request for Review Form
|
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
|---|
| Project title of the project activity or programme of activities (PoA) for which issuance is requested | LDEO Biomass Steam and Power Plant in Malaysia (0395) |
|---|---|
| DOE that requested for issuance and date of request | DNV (14 Jul 08) |
| Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
| Incompetence | |
| Please indicate reasons for the request for review | |
|
1. The monitoring report states that the emission reductions are based on the amount of steam generated by the biomass boiler, methane emissions avoided by project and electricity displaced. However, the DOE states in the verification report (p.4 -5) that the electrical energy supplied to the refinery by the biomass plant is not monitored and emissions reductions are based on the amount of steam generated and methane emissions avoided. Clarification by the DOE is required taking into consideration that this issue was raised in the previous request for issuance. 2. The verification report (p 4) stated the completeness of monitoring based on the monitoring plan in the registered PDD (dated 18 April 2006) rather than the revised monitoring plan approved on 17 June 2008. Clarification by the DOE is required. |
|
| Date | 14 Aug 08 |