14:50 11 Jan 25
Project:
0386 Seguntor Bioenergy 11.5MW EFB Power Plant
- Issuance Request
Project | 0386: Seguntor Bioenergy 11.5MW EFB Power Plant |
---|---|
ISSUANCE STATUS | Issued (on 11 Feb 14) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Aug 12 - 31 Dec 12 |
Monitoring report | Monitoring report (354 KB) |
Request for issuance | Signed form (778 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
166,377
Serial Range:
Block start: MY-5-7935708-1-1-0-386
Block end: MY-5-8102084-1-1-0-386
|
Verification and certification reports |
VVS/VVM version:
VVS 4.0
Certification report (320 KB) Verification report (320 KB) |
Additional documents |
Final Monitoring Report (188 KB)
Final ER Spreadsheet (550 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: