04:17 24 Nov 24
Project:
0362 Sri Balaji 6 MW Non-Conventional Renewable Sources Biomass Power Project
- Issuance Request
Project | 0362: Sri Balaji 6 MW Non-Conventional Renewable Sources Biomass Power Project |
---|---|
ISSUANCE STATUS | Issued (on 20 Feb 08) |
Monitoring period | 25 Nov 06 - 24 Sep 07 |
Monitoring report | Monitoring report (39 KB) |
Request for issuance | Signed form (678 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
24,830
Serial Range:
Block start: IN-5-34910650-1-1-0-362
Block end: IN-5-34935479-1-1-0-362
|
Verification and certification reports |
Certification report (99 KB)
Verification report (99 KB) |
Additional documents |
MR (92 KB)
doc (184 KB) |