19:13 03 Oct 24
Project:
0362 Sri Balaji 6 MW Non-Conventional Renewable Sources Biomass Power Project
- Issuance Request
Project | 0362: Sri Balaji 6 MW Non-Conventional Renewable Sources Biomass Power Project |
---|---|
ISSUANCE STATUS | Issued (on 25 Mar 20) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 May 16 - 30 Apr 17 |
Monitoring report | Monitoring report (645 KB) |
Request for issuance | Signed form (36 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
21,404
Serial Range:
Block start: IN-5-256919564-2-2-0-362
Block end: IN-5-256940967-2-2-0-362
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 2.0
Certification report (310 KB) Verification report (310 KB) |
Additional documents |
Untitled (uploaded 29 Dec 19 20:29:05) (50 KB)
Untitled (uploaded 29 Dec 19 20:29:05) (404 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: