Project: 0349 Sihwa Tidal Power Plant CDM Project - Issuance Request
Project 0349: Sihwa Tidal Power Plant CDM Project
 
ISSUANCE STATUS Issued (on 09 Jun 16)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Apr 15 - 30 Sep 15
Monitoring report Monitoring report (568 KB)
 
Request for issuance Signed form (912 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 160,115
Serial Range: Block start: KR-5-147730199-2-2-0-349     Block end: KR-5-147890313-2-2-0-349
Verification and certification reports VVS/VVM version: VVS 9.0
Certification report (376 KB)
Verification report (376 KB)
Additional documents MR_Siwha (592 KB)
BM sheet_Siwha (105 KB)
ER sheet_Sihwa (31 KB)