14:39 03 Feb 26
Project:
0349 Sihwa Tidal Power Plant CDM Project
- Issuance Request
| Project | 0349: Sihwa Tidal Power Plant CDM Project |
|---|---|
| ISSUANCE STATUS | Issued (on 29 Oct 15) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Oct 14 - 31 Mar 15 |
| Monitoring report |
Monitoring report (467 KB)
|
| Request for issuance |
Signed form (488 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
163,910
Serial Range:
Block start: KR-5-134020040-2-2-0-349
Block end: KR-5-134183949-2-2-0-349
|
| Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (381 KB)
Verification report (381 KB)
|
| Additional documents |
BM sheet_ver02 (108 KB)
ER sheet_ver02 (30 KB)
MR_ver02 (742 KB)
|

Monitoring report
BM sheet_ver02
Offset now: visit the United Nations Carbon Offset Platform