ISSUANCE STATUS Issued (on 29 Oct 15)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Oct 14 - 31 Mar 15
Monitoring report Monitoring report (467 KB)
 
Request for issuance Signed form (488 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 163,910
Serial Range: Block start: KR-5-134020040-2-2-0-349     Block end: KR-5-134183949-2-2-0-349
Verification and certification reports VVS/VVM version: VVS 9.0
Certification report (381 KB)
Verification report (381 KB)
Additional documents BM sheet_ver02 (108 KB)
ER sheet_ver02 (30 KB)
MR_ver02 (742 KB)