Project: 0349 Sihwa Tidal Power Plant CDM Project - Issuance Request
Project 0349: Sihwa Tidal Power Plant CDM Project
 
ISSUANCE STATUS Provisional (awaiting guidance from the CMP at CMP 16)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jul 21 - 30 Jun 22
Monitoring report Monitoring report (622 KB)
 
Request for issuance Signed form (524 KB)
Amount of CERs CERs from 01 Jan 2021: 216,822
Verification and certification reports VVS/VVM version: VVS-PA 3.0
Certification report (629 KB)
Verification report (629 KB)
Additional documents ER calculation sheet_v.2 (48 KB)
Monitoring report_v.2.0 (622 KB)