12:22 02 Dec 24
Project:
0349 Sihwa Tidal Power Plant CDM Project
- Issuance Request
Project | 0349: Sihwa Tidal Power Plant CDM Project |
---|---|
ISSUANCE STATUS | Provisional (awaiting guidance from the CMP at CMP 16) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 21 - 30 Jun 21 |
Monitoring report | Monitoring report (604 KB) |
Request for issuance | Signed form (391 KB) |
Amount of CERs |
CERs from 01 Jan 2021:
119,465
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 3.0
Certification report (527 KB) Verification report (527 KB) |
Additional documents |
ER sheet (35 KB)
Monitoring Report_ver.3.0 (609 KB) |