Project: 0349 Sihwa Tidal Power Plant CDM Project - Issuance Request
Project 0349: Sihwa Tidal Power Plant CDM Project
 
ISSUANCE STATUS Issued (on 21 Jul 21)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jul 20 - 31 Dec 20
Monitoring report Monitoring report (607 KB)
 
Request for issuance Signed form (393 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 118,548
Serial Range: Block start: KR-5-185294419-2-2-0-349     Block end: KR-5-185412966-2-2-0-349
Verification and certification reports VVS/VVM version: VVS-PA 2.0
Certification report (604 KB)
Verification report (604 KB)
Additional documents ER_sheet (33 KB)
MR_Ref.0349 MP18_v02 (810 KB)