Project: 0349 Sihwa Tidal Power Plant CDM Project - Issuance Request
Project 0349: Sihwa Tidal Power Plant CDM Project
 
ISSUANCE STATUS Issued (on 22 Jul 20)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jul 19 - 31 Dec 19
Monitoring report Monitoring report (593 KB)
 
Request for issuance Signed form (380 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 125,127
Serial Range: Block start: KR-5-182572742-2-2-0-349     Block end: KR-5-182697868-2-2-0-349
Verification and certification reports VVS/VVM version: VVS-PA 2.0
Certification report (882 KB)
Verification report (882 KB)
Additional documents MR_ref.0349_MP16 (626 KB)
ER_ref.0349_MP16 (34 KB)