Project: 0349 Sihwa Tidal Power Plant CDM Project - Issuance Request
Project 0349: Sihwa Tidal Power Plant CDM Project
 
ISSUANCE STATUS Issued (on 23 Jan 20)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jan 19 - 30 Jun 19
Monitoring report Monitoring report (837 KB)
 
Request for issuance Signed form (415 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 119,202
Serial Range: Block start: KR-5-180723360-2-2-0-349     Block end: KR-5-180842561-2-2-0-349
Verification and certification reports VVS/VVM version: VVS-PA 2.0
Certification report (548 KB)
Verification report (548 KB)
Additional documents monitoring report (630 KB)
ER calculation spreadsheet (33 KB)