16:56 22 Nov 24
Project:
0346 Nueva Aldea Biomass Power Plant Phase 2
- Issuance Request
Project | 0346: Nueva Aldea Biomass Power Plant Phase 2 |
---|---|
ISSUANCE STATUS | Issued (on 29 Oct 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Oct 08 - 31 Dec 09 |
Monitoring report | Monitoring report (444 KB) |
Note:
Issuance request(s) for this monitoring period have been previously considered: - Status: Withdrawn (Request for review period: 07 May 11 - 03 Jun 11) |
|
Request for issuance | Signed form (159 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
147,803
Serial Range:
Block start: CL-5-10083837-1-1-0-346
Block end: CL-5-10231639-1-1-0-346
|
Verification and certification reports |
VVS/VVM version:
VVM 1.2
Certification report (1345 KB) Verification report (1345 KB) |
Additional documents |
5j NAF-2CP1 MP3120622ver2 _clean_ (817 KB)
6n - NAF-2monitCP1MP3120522ver2 (2) (44 KB) Spreadsheets (1507 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: