10:07 24 Apr 24
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Nueva Aldea Biomass Power Plant Phase 2 (0346) |
---|---|
DOE that requested for issuance and date of request | SGS (09 Mar 09) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
The DOE is requested to clarify how it verified: (i) That the choice of using simple adjusted Operating Margin (OM) is in accordance with the applied methodology ACM0002, which specifies dispatch data analysis as the first methodological choice for OM calculation. (ii) The appropriateness of calculation of CERs for the year 2008 using grid emission factor calculated based on only nine months data for the year 2008. (iii) The natural gas consumption in the project as the emission reduction spreadsheet does not include any values. |
|
Date | 06 Apr 09 |