Project: 0298 4.5 MW Biomass (low density Crop Residues) based Power Generation unit of Malavalli Power Plant Pvt Ltd. - Issuance Request
Project 0298: 4.5 MW Biomass (low density Crop Residues) based Power Generation unit of Malavalli Power Plant Pvt Ltd.
 
ISSUANCE STATUS Issued (on 10 Jun 10)  
Monitoring period 01 Aug 08 - 30 Apr 09
Monitoring report Monitoring report (21 KB)
 
Request for issuance Signed form (491 KB)
Amount of CERs CERs issued up to 31 December 2012: 9,211
Serial Range: Block start: IN-5-78894795-1-1-0-298     Block end: IN-5-78904005-1-1-0-298
Verification and certification reports Certification report (162 KB)
Verification report (162 KB)
Additional documents 298_MR_revised (77 KB)
Fuel Data 0298 (39 KB)
298_Electricity bill details_rev (48 KB)