18:00 30 Dec 24
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Bundled wind power project in Chitradurga (Karnataka in India) managed by Enercon (India) Ltd. (0276) |
---|---|
DOE that requested for issuance and date of request | BVI (19 Apr 11) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
It was noted that the electricity generated during the present monitoring period spanning more than two years was 8.55% higher than the estimated in the PDD, and this increase was also noted during the first monitoring period (the project generated 8.4% more electricity) and during the second monitoring period (the project generated 11.77% more electricity than estimated). The PP in the monitoring report explained that this was “due to a higher PLF” and the DOE in the verification report stated that the “average PLF during the monitoring period is about 31.81%”. The PP/DOE should further explain if the project was operated as per the PDD given that the sensitivity analysis in the PDD was done considering a variation in the PLF in the range between 26 to 30%. | |
Date | 11 Jun 11 |