Project: 0259 Trupan Biomass Power Plant in Chile - Issuance Request
Project 0259: Trupan Biomass Power Plant in Chile
 
ISSUANCE STATUS Issued (on 31 Jul 15)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jan 13 - 31 Dec 13
Monitoring report Monitoring report (743 KB)
Requests for post-registration changes containing applicable deviations PRC-0259-003 - Approved
Requests for post-registration changes submitted with the issuance request PRC-0259-003
 
Request for issuance Signed form (65 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 128,473
Serial Range: Block start: CL-5-21681431-2-2-0-259     Block end: CL-5-21809903-2-2-0-259
Verification and certification reports VVS/VVM version: VVS 7.0
Certification report (3793 KB)
Verification report (3793 KB)
Additional documents 3f_Trupan monit CP2-MP3 ver6 150303.xls (171 KB)
48c_Emission Factor SIC 2013 ACM0002 Ver10 (Trupán) ver2.xlsx (1169 KB)
4g_Monrep Trupan CP2 MP3 150303 ver7 (1177 KB)